Checked against Town, County and HOA sources on October 22, 2026. Rules change, so confirm with the office named in each step.
A remodel in Castle Rock can need sign-off from two places that don't coordinate: the Town's Building Division and your homeowners association. This guide covers both, in the order they usually come up, with a link to the official page behind each rule.
1. Confirm who issues your permit
A Castle Rock mailing address can sit outside Town limits. Open Douglas County's property map, search your address, choose Assessment Details, expand the Account Summary and find the Building Permit Authority. If it says Town of Castle Rock, keep reading. If it names another agency, that agency's rules apply. Unincorporated Douglas County is covered at the end.
2. Does your project need a permit?
The Town lists remodels among the common home projects that need a building permit and says permits are required by Town code. It doesn't list every scope, so describe yours on the Building Counter help form and let staff confirm.
Related points from the Town's residential permit page:
- Furnace, air conditioner, water heater, water softener and re-roof permits may skip plan review. A general remodel isn't on that list.
- Moving or adding a gas range? Read the Town's Gas Line Appliance Checklist.
- Since July 1, 2026, the 2025 Colorado Wildfire Resiliency Code can add requirements to certain exterior renovations, depending on the property's fire-intensity class. If an outside wall changes, check the state's wildfire resiliency map.
- In the historic downtown area (east of I-25, west of Gilbert Street, south of Wolfensberger Road and generally north of South Street), the Historic Preservation Board reviews alterations to existing structures. Ask the Town's planning staff before changing the outside.
The Town builds to the 2024 International Residential Code and the 2026 National Electrical Code, with local amendments in effect since June 30, 2026.
3. Who can apply
You, as the homeowner. Only for a house you own and live in; rentals don't qualify. You sign a Homeowner Affidavit in person at the Building Counter in Town Hall, or have it notarized to submit online. Only you may sign it, and you answer for the work meeting code.
A contractor. Before applying, a contractor needs a license from a jurisdiction with an ICC-equivalent exam, liability insurance, workers' compensation where it applies, and a current Town registration. The Town calls work by unregistered, unlicensed contractors unlawful. You can check a registration in eTRAKiT, and plumbers and electricians also need state licenses.
4. Applying in eTRAKiT
Create a public account in the eTRAKiT Development Portal, choose Apply / New Permit and follow the prompts. Under the Town's electronic submittal rules, the plan set goes in as one flattened, unlocked PDF bookmarked by sheet, with supporting documents as separate PDFs. Changes made during review are uploaded as a full new version, with the changes clouded.
The Town has warned of an email scam aimed at eTRAKiT applicants, so verify any odd permit email with the Building Counter.
5. What the Town charges
The permit fee comes from a valuation table in the Town's 2026 fee schedule, effective July 1, 2026. The square-foot valuation table is for new construction, so an alteration is valued at its cost. Plan review adds 65% of the permit fee. Building use tax is 5.2% (4.2% Town, 1% Douglas County) on half the valuation, which the Town treats as the materials share.
| Project valuation | Permit fee | Plan review (65%) | Use tax (5.2% of half) |
|---|---|---|---|
| $25,000 | $391.25 | $254.31 | $650.00 |
| $50,000 | $643.75 | $418.44 | $1,300.00 |
| $100,000 | $993.75 | $645.94 | $2,600.00 |
Worked from the schedule; the Town calculates each actual fee.
- Use tax is usually collected when the permit is issued. Show the permit when you buy materials, and the supplier shouldn't charge Town and County sales tax on them. If a supplier did, the Town accepts refund applications with copies of the receipts.
- Fees and taxes based on valuation are due on the final cost, and the Town suggests reconciling when the permit closes.
- A re-inspection costs $85 or $170.
6. Inspections
Request inspections in eTRAKiT up to 6:30 a.m. on the day you want them, or on the Town's inspection hotline by 3:30 p.m. for the next business day. The site has to be open from 7:30 a.m. to 5 p.m. that day. There are no inspections on Town holidays; the rest of 2026 has Nov. 11, Nov. 26 and 27, and Dec. 25.
7. HOA approval
Find your association. The Town has mapped more than 150 neighborhoods, and its Neighborhoods Map shows association and management links for each. A metro district is not an HOA: the Town describes metro districts as separate taxing entities, mostly formed by developers to pay for infrastructure.
Know what it reviews. Design review here centers on the outside of the house. Castlewood Ranch's guidelines, for example, define a reviewable change as an exterior change. They require approval before work starts for new windows and for rooftop equipment such as vents, and they allow moving pods for one week. The committee meets at least monthly and generally mails a decision within 10 business days of the meeting. If 30 days pass after a complete application with no answer, the owner notifies the committee, and a request still unanswered 10 days later is deemed approved. Approved work should be finished within 12 months. Other associations set their own clocks, so read yours.
Two separate approvals. Castlewood's guidelines say the committee's approval doesn't cover building codes or government approvals, so plan for both.
8. Neighbors, noise and the street
Construction tools and equipment may run from 7 a.m. to 7 p.m. on weekdays and from 8 a.m. to 6 p.m. on weekends and holidays. Materials and debris stay on your property, not in the street or right-of-way. If a dumpster can't fit on the driveway, ask the Town first. The fee schedule lists a $75 charge for obstructions in the right-of-way, right-of-way permits go through eTRAKiT, and a sidewalk closure needs an application at least a week ahead.
9. Outside Town limits
Douglas County's Building Division issues permits for unincorporated areas. It reviews simple residential interior remodels over the counter on weekday mornings, 8 a.m. to noon. A complete application with no plan problems typically takes 7 to 10 business days. A County permit expires if no inspection is requested for 180 days, and contractors must be registered with the County.
Quick checklist
- Confirm the Building Permit Authority on the County map.
- Read your HOA's guidelines; apply first if the outside will change.
- Ask the Town whether your scope needs a permit.
- Check the contractor's Town registration and trade licenses.
- Apply in eTRAKiT and pay the fees and use tax.
- Keep a copy of the permit for material purchases.
- Book inspections and keep the site open 7:30 a.m. to 5 p.m.
- Close the permit and reconcile it against the final cost.
For the order a kitchen job follows, see the kitchen remodeling step-by-step guide.